Further delays anticipated as surprise bids submitted for interconnector

Meanwhile, power cuts already start to hit the island as temperatures soar

 

The installation of a second electricity interconnector between Malta and Sicily, already delayed by a year, is expected to be delayed further.

A multi-million-euro tender issued by the government has unexpectedly attracted bidders with no track record in the industry who submitted unrealistic bids in an attempt to be awarded the massive contract.

While the tender has an indicative value of €68 million, a Sardinia-based Italian company, SELT S.P.A. – sistemi elettrici telefonici – has submitted a bid for just half the tender’s value – €34 million.

The Shift is informed that this has raised eyebrows among the top executives of Interconnect Malta – the government entity responsible for the project’s execution.

While the bid may look attractive to the Maltese taxpayer at first glance, sources at Interconnect Malta described it as “very suspicious” not only because the price is commercially unfeasible but also because of the company’s lack of experience in the field.

They also said the bid is too low and impossible to achieve, and it may further delay the completion of the project given that the evaluation will take time and thorough due diligence will be required.

According to the sources, SELT has never completed a project of the magnitude required for Malta’s interconnector.

Meanwhile, another low bid was submitted by a Chinese company, Hengtong Optic-Electric Co Ltd – which, if chosen, may put Malta at loggerheads with the EU since the project is financed through EU funds.

The tender is for laying some 25 kilometres of underground cable, both in Malta leading to the Maghtab land base and in Sicily leading to the base station in Ragusa.

Although the work should be easier than when the first interconnector was laid, as the foundations for a second cable were already prepared by the PN administration in 2012, the job is of significant complexity.

Five companies have submitted bids, with Bonnici Brothers being the only Maltese company in the competitive process. However, the company’s bid, at €64.3 million, is the most expensive, making it unlikely to be declared the winner.

Bids submitted for the €68 million tender.

Enemalta has already awarded the same company a lucrative tender to install a temporary diesel-fired power plant in Delimara to compensate for the lack of energy availability caused by the delay in installing the second interconnector.

Already a year late

In 2021, Energy Minister Miriam Dalli announced the government’s decision to increase Malta’s electricity capacity in response to rising demand. The chosen expansion option was the implementation of a second interconnector.

Dalli had stated that the second interconnector was to be up and running by the summer of 2025.

However, the Energy Minister’s plans have already gone awry. The installation of the interconnector is already 12 months behind schedule, and the latest complications with the new onshore works tender are expected to complicate matters further.

An expensive temporary solution

Following last summer’s debacle, when the country was caught unprepared for increased demand, with consistent power cuts across the country for many days, Enemalta awarded a rushed €37 million tender to install a temporary power plant this summer.

The emergency power plant, leased until the new interconnector is ready, will be supplied by Bonnici Brothers through a Saudi company and used only when the electricity produced locally and through the interconnector is insufficient to meet the demand.

Instead of choosing a cleaner solution, including Liquified Natural Gas (LNG), already available at Delimara, the government opted for Bonnici’s diesel-fired plant, using one of the most polluting fuels on the market.

Bonnici, who has no experience in the area, is closely connected to Prime Minister Robert Abela, who served as the company’s lawyer and was also in business with its managing director, Gilbert Bonnici.

Enemalta Chair Ryan Fava said the temporary plant had to be installed by last May, but this has not yet happened.

In the meantime, Malta experienced its first nationwide power cut of the summer a few days ago, which, according to Minister Miriam Dalli, was caused by maintenance on the current interconnector.

Sign up to our newsletter

Stay in the know

Get special updates directly in your inbox
Don't worry we do not spam
Subscribe
Notify of
guest

12 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Karmenu Psaila
Karmenu Psaila
6 months ago

So the Italian company has lack of experience, but do Bonnici Brothers have experience? Or they will pass the work to a sub contractor like what most contractors do to most of our awarded tenders . Sometimes they form a cartel although it is not legal. So eyes open .

George Said
George Said
6 months ago
Reply to  Karmenu Psaila

They form a consortium or sub- contract which are 2 different options. Nonetheless it is permissible in EU procurement for a partner or a sub- contractor to fulfill the experience criterion when submitting a tender.

Gordon Cook
Gordon Cook
6 months ago

I wonder if Vitalis have bid……
But then the gang are not involved in the decision this time

S. Camilleri
S. Camilleri
6 months ago

“the government opted for Bonnici’s diesel-fired plant, using one of the most polluting fuels on the market.” or, how to substitute one cancer factory with another.
“Bonnici, who has no experience in the area, is closely connected to Prime Minister Robert Abela, who served as the company’s lawyer and was also in business with its managing director, Gilbert Bonnici.”: friends of friends anyone?

Mark
Mark
6 months ago

as you can see, almost all offers are much lower than the initial price…

Out of Curiosity
Out of Curiosity
6 months ago

If the evaluation committee finds that some of the bidders have no experience in completing similar projects they should simply consider them as administratively non compliant, as such requirement must be clearly indicated in the tender document to make sure that only competent bidders submit a bid. This is no rocket science.

Albert Bonnici
Albert Bonnici
6 months ago

Miriam Dalli is the worst incompetent Minister ever.

Joseph
Joseph
6 months ago
Reply to  Albert Bonnici

100% agree

makjavel
makjavel
6 months ago

What the minister stated , and it is true , the EneMalta side of the interconnector was being maintained. The work was done on three consecutive days, 15th , 16th 17th. The interconnection is being continuously used and sometimes the maximum was reached.
The support to the grid from the 200MW PV installation during sunny hours is also obvious. It also obvious that switching off in some areas starts in the evening when the 200 MW Solar Power stops. Conclusion, Malta does not have security of supply. This is all the Fault of this Minister going along with Konrad Mizzi and Joseph Muscat and Robert Abela destroying the Delimara PS Phase 1.

wenzu
wenzu
6 months ago

Miriam Dalli, Miriam Dalli! whenever this name crops up, it is associated with cock-ups galore.

Sandra Vella
Sandra Vella
6 months ago
Reply to  wenzu

Is that why she always has a ‘fake’ smile????

Bernard Manduca
Bernard Manduca
6 months ago

Oh dear. Sardinia. This could be the stage where any local corruption would be controlled by foreign corruption. Taken over, in fact.

Related Stories

Opinion: Wanton vandalism
In 2021, Afghanistan’s Taliban blew up the ancient statues
Critics slam St John’s €70,000 crib, question authenticity, personal interests
Experts in Malta’s cultural heritage, art, and baroque architecture

Our Awards and Media Partners

Award logo Award logo Award logo