Summer construction ban amended to allow for Mistra Village development

The Malta Tourism Authority and Building and Construction Authority scheme stopping excavation and construction during the summer months in “tourist zones” was altered this year to allow the controversial development at the former Mistra Village hotel site in Xemxija to continue throughout the summer.

An analysis of the MTA lists of the last three years of streets in which no construction work may be done throughout the summer period shows that streets abutting the site had specific exemptions included, while others were removed from the list entirely, allowing for the development to continue.

The permit for the project by Charles Camilleri of Gemxija Crown Ltd for a 12-storey residential and commercial complex with over 700 apartments, was revoked by the Chief Justice in the Court of Appeals in May.

Chief Justice Mark Chetcuti sent the case back to the Environment and Planning Review Tribunal to consider whether the project is still compatible with current planning laws and policies.

Meanwhile, the work on the site is ongoing, with residents complaining about noise and dust lasting until the evening on summer nights.

Comparing the lists of streets on which construction is paused for the summer period on a map clearly shows exemptions were explicitly included to allow for the Mistra Village development.

Telgħet ix-Xemxija, Trejqet il-Fuħħar and Triq Katerina Vitale were all conspicuously missing from the 2023 list despite being included in 2021 and 2022.

For this year, Triq il-Mistra includes an exemption between Telgħa ta’ Selmun up to Triq ix-Xemxija, while construction on Triq Raddet ir-Roti is only banned up to Trejqet Għar Berbaħ.

The ‘summer break’ scheme was introduced by the Malta Tourism Authority in 2021 alongside a substantial advertising campaign to quell public outcry against overdevelopment and mitigate the industry’s negative impacts in tourist areas.

Last week, The Shift reported how noise pollution and fine dust from works on the project have been affecting people living in neighbouring streets, with one resident telling The Shift works were ongoing “Monday to Saturday, from 7 am to 6 pm”.

The EPRT accepted a site visit requested by the residents in July, but the commitment has not been fulfilled.

Lawyer Claire Bonello, representing the residents in their appeal against the development, told The Shift that the developers have expedited works on the site before the visit to prove the commitment called for by the courts, placing residents in “a fight against time”.

                           

Sign up to our newsletter

Stay in the know

Get special updates directly in your inbox
Don't worry we do not spam
                           
                               
Subscribe
Notify of
guest

4 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
John debono
John debono
7 months ago

Corruption at its best.Money talks. Building contractors do what they please they are above the law.

John C.
John C.
7 months ago

On Xlendi its a nightmare. Construction, dust and noises from 6am to 8pm even Saturdays and Sundays with no enforcement at all. It’s scandalous to say the least.

Anne R. key
Anne R. key
7 months ago

Yesterday Saturday, close to the National Aquarium, construction went on from early in the morning until the afternoon – there is no ban and no enforcement! And no rest for the weary.

James Vella
James Vella
7 months ago

That is what happed in Marsascala. Before the project in Triq il Ghaguza began the permission was given to continue excavations during the summer months. Effectively just in front of the sea.

Related Stories

BA directive against Roberta Metsola ‘unprecedented’, must be suspended
The European Parliament office in Malta has reacted to
From Naxxar to Namibia: Councillor to be appointed ambassador
Malta’s Foreign Minister Ian Borg has nominated a Labour

Our Awards and Media Partners

Award logo Award logo Award logo